8月29日(ri),隨著(zhu)池祁高速大洪嶺2號特(te)長隧道(dao)右幅(fu)瀝(li)青(qing)路面上(shang)面層(ceng)攤(tan)鋪順利完工,該(gai)項(xiang)目53.656公里主線瀝(li)青(qing)面層(ceng)施工圓滿(man)完成,路面主體(ti)工程施工結(jie)束,為項(xiang)目年內建成通車奠定了堅實基礎。
今年以來,池祁高速建(jian)(jian)設者繼續(xu)發揚(yang)“知(zhi)重負重、敢于攻堅(jian),苦干(gan)實干(gan)、勇當先鋒”的(de)縣縣通攻堅(jian)精神,全力以赴(fu)推進項(xiang)目建(jian)(jian)設。截至目前,路(lu)基、橋梁、隧(sui)道(dao)、主線路(lu)面(mian)工(gong)程已(yi)全部(bu)完(wan)成(cheng)(cheng)(cheng)(cheng);交安基礎及(ji)立柱完(wan)成(cheng)(cheng)(cheng)(cheng)99%,掛(gua)板完(wan)成(cheng)(cheng)(cheng)(cheng)93%,標志(zhi)安裝(zhuang)完(wan)成(cheng)(cheng)(cheng)(cheng)89%;中分帶(dai)綠化(hua)完(wan)成(cheng)(cheng)(cheng)(cheng)98%,站區綠化(hua)完(wan)成(cheng)(cheng)(cheng)(cheng)60%;收(shou)費、通信、監控等三(san)大(da)系統(tong)機電(dian)完(wan)成(cheng)(cheng)(cheng)(cheng)80%,隧(sui)道(dao)機電(dian)完(wan)成(cheng)(cheng)(cheng)(cheng)85%;場區房建(jian)(jian)完(wan)成(cheng)(cheng)(cheng)(cheng)93%,收(shou)費站大(da)棚90%,隧(sui)道(dao)配電(dian)房完(wan)成(cheng)(cheng)(cheng)(cheng)100%。