近日,寧安高速安徽段(duan)汪家村大橋右幅順利(li)貫通(tong),為項目貫通(tong)奠定了(le)堅實的基礎。
汪家村大橋位于(yu)K4+040處(chu),上跨S104省(sheng)道,右幅全長(chang)823.5米,預(yu)制(zhi)梁(liang)(liang)板共(gong)計108片(pian)。下(xia)部構(gou)造(zao)采用門架墩形式跨越S104省(sheng)道,施(shi)工(gong)(gong)難度大、風險高,現場安全吊裝要求嚴苛。項(xiang)目辦倒排工(gong)(gong)期,合(he)理安排下(xia)部構(gou)造(zao)施(shi)工(gong)(gong)順(shun)序(xu)(xu)及(ji)上部箱梁(liang)(liang)預(yu)制(zhi)、保(bao)養、轉運、吊裝工(gong)(gong)序(xu)(xu),并在施(shi)工(gong)(gong)中(zhong)不(bu)斷優化(hua)方案,緊盯關(guan)鍵部位和(he)關(guan)鍵工(gong)(gong)序(xu)(xu),確(que)保(bao)箱梁(liang)(liang)架設連續(xu)穩(wen)步(bu)推進。2022年(nian)1月16日吊裝第一片(pian)箱梁(liang)(liang),歷時8個月順(shun)利完成大橋右幅預(yu)制(zhi)箱梁(liang)(liang)吊裝。